Sunday 18 February 2018

FRWA- FAQS BY BUYERS BASED ON HARASSMENT BY BUILDERS


KULDEEP KUMAR KOHLI
PRESIDENT
FEDERATION OF RESIDENTS WELFARE ASSOCIATION
08860332402
FORFORWA@GMAIL.COM



FAQs by buyers based on harassment by builders

May these answers be construed as prima facie basic responses based on the limited information provided to us as on date by the members and members are advised to consult their Legal Counsel as well

Q. 1 If a person has been given the possession letter after a delay can he file the case for interest but he has not taken the possession?
Ans. 1       Yeshe can file a case for claiming interest for delay in granting Possession.

It is however advised that the Buyer should take possession if the construction is complete in all sense to the satisfaction of the Buyer and then the Buyer can proceed with taking action against the builder for claiming interest for delay in possession.

It is a common practice that even before the flats are ready, developers roll out the “Offer of Possession“. The actual possession of apartment happens after months of making final payments. Sometimes the possession is delayed further for reason like no Occupancy Certificate etc. Developers may give various excuses like the fitting and fixtures shall only be installed after final payment.[1]

The consumer / flat buyers cannot be forced to accept possession of the unit, offered at a belated stage, in the absence of any force majeure circumstances.[2]

It is also to be noted that in case a person / consumer denies to take possession of their property on being offered the same from the builder, a concrete reason / deficiency needs  to be pointed out  to enable the consumer to later accept the possession and claim interest for delay also.  

Q.2   What happens to a person who has taken the possession after a delay, having signed the indemnity bond?

Ans.2 Indemnity bond shall be executed by the Builder in favour of the buyer/s. Hence signing of Indemnity Bond is in the interest of the buyers.

Q. 3  One person bought the property from another and got a delayed possession. Can he file the case?   He has taken the possession.

Ans. 3      Yes, The subsequent buyer steps into the shoes of the previous buyer and hence all the  rights and entitlements which the previous buyer would have claimed, the subsequent buyer would be entitled to the same. In any case, the subsequent buyer would ‘buy the risks’ inherent with a property and that is the reason the subsequent buyer would usually purchase the property at a higher rate.

The answer to this question depends on the time when the re-sale was given effect to. Although the Subsequent Buyer of the Property has the right to claim interest from the builder but the rate at which such claim can be made depends upon the time when the re-sale happened.

Q.4   A person was offered possession four years beyond the delivery period and he is not taking possession because he wants interest what happens to his case.

Ans. 4      The answer to this question is same as that of 1. The claim for interest will survive irrespective of whether possession has been taken or not by the Buyer.


Q.5.  What happens to a person who has two properties? Will it be termed as commercial or he will be considered a consumer on the act.

Ans.5        Please refer to the judgment of Laxmi Engineering Works vs P.S.G. Industrial Institute on 4 April, 1995, Equivalent citations: 1995 AIR 1428, 1995 SCC (3) 583. The person may not be considered a consumer in the eyes of law. At times however if the property has not been bought from the same builder, the builder may or may not make this claim of the buyer/complainant owning second property.

A buyer who already has 2 Properties will be considered as a consumer under the act provided the Buyer does not trade in buying and selling houses on a regular basis for commercial gains.

Q.6   What happens to a person who is living in his own house and this is second or third property in his own name. Does he still get the interest inn case of delay in handing over possession and the Buyer denies taking the possession: the question was whether the Buyer can file a case for claiming Interest?

Ans.6       The answer would be same as above. (Please refer to answer to the question 5 and Laxmi Engineering Judgment)

Q.7   Under which section is a buyer covered under the Consumer Protection Act/Rules.

Ans.7        In terms of Section 2(1)(d)  of the Consumer Protection Act, 1986

Q. 8.          If the builder whose services are engaged by a buyer for construction of a residential house for him fails to complete the construction and deliver its possession on or before the date committed by him for the purpose, would such an act on the part of the builder be termed as an act of negligence, causing loss or injury to the flat buyer.

Ans. 8       Yes, The term “negligence” has not been defined in the Consumer protection Act but as per its dictionary meaning, it is the failure to give enough care or attention especially when such an act has serious results to another person.   (Oxford Advanced Learner’s Dictionary, New 8th Edition).  As per Black’s Law Dictionary IX Edition, negligence includes the failure to exercise the standard of care that a reasonably prudent person would have exercised in a similar situation.
Hence in the absence of force-majeure circumstances, a prudent builder would have been in a position to construct the flats and offer their possession to the buyer on or before the date committed or at best within the grace period under the BBA.  By not delivering on the commitment made by it with respect to the delivery of the possession of the flats booked by the buyers, the builder certainly commits an act of negligence and since the said act of negligence results in loss or injury to the buyer who is deprived of the use of the flats booked by them, compensation in terms of 14(1)(d) of the Consumer Protection Act may be awarded to the buyer.

Furthermore since the Act empowers the Commission to direct removal of the deficiencies in the services,  in exercise of the afore said power of the Commission, the builder can also be directed and in fact ought to be directed to complete the construction and deliver possession of the flat to the buyer at the earliest possible.  Therefore both the directions sought by the buyers viz. direction for completion of the construction and delivery of possession of the flats and the direction for payment of compensation for the period, the possession is delayed are within the competence of the NCDRC under section 14 of the Consumer Protection Act.

Such a delay on the part of the builder would tantamount to deficiency in service in terms of 2(1)(g) of Consumer Protection Act, 1986.

Q. 9 Would it be correct to say that the buyer approaching the NCDRC are asking for specific performance of the Agreement the buyers executed with the builder.

Ans.9. No, the specific performance of a contract can be sought before a Civil Court in terms of the provisions contained in the Specific Relief Act 1963.  Neither is the NCDRC a Civil Court not do the buyers invoke the provisions of the Specific Relief Act, 1963.

Q 10.         Is the person entitled for interest as compensation if he has bought the property in re-sale?

Ans. 10 Yes, the buyer steps into the shoes of the original buyer and hence is entitled for the   interest as compensation.

Q. 11         The builder first takes three instalments as advance and then sends the BBA for signatures which the buyer is bound to sign.  The time period of construction mentioned in the BBA starts from the date BBA is signed.  Is the person entitled for the interest for the first three instalments till the time the BBA is signed?

Ans. 11     Interest is usually awarded on the payment made which is calculated from the date of deposit till the date of realisation of the amount ordered by the Forum/Commission.
However interest on refund is treated differently from interest on delay. On delay the interest is usually awarded from the date of promised date of possession.

Q.12 Is giving the money as advance to the builder tantamount to acceptance of the offer and hence a contract is established

Ans. 12 Yes. A contract is certainly established. The builders are known to treat the buyers as captive buyers and hence they are left with no option but to dance to the tune of the builder. Thus in BBA the buyers don’t usually get any opportunity to negotiate the terms of the Agreement which goes contrary to the spirit of an enforceable contract.

Q. 13         What is the limitation within which you can approach RERA or NCDRC after having taken the possession?

Ans 13.To invoke Consumer Protection Act the limitation is 2 years from the date of cause of action whereas to invoke RERA the limitation is as per the Limitation Act, 1963 i.e. 3 years. It is to be noted that in terms of Section 19(10) every allottee is supposed to take physical possession of the property within a period of two months of the occupancy certificate issued by the government. It is advisable to invoke Consumer Protection Act in such situations where the defect/deficiency is on account of some latent defect in the property.

Q. 14         Should a consumer approach the State under RERA or go to the National Consumer for Relief.

Ans.14      It would depend upon the relief sought. At the moment jurisprudence related to RERA is still in the infancy and much has been left to the discretion of the authorities. At the same time however RERA can conduct investigation etc. whereas Consumer Fora cannot do that. Owing to a developed jurisprudence of Consumer Protection Act however the ease of handling of litigation is much more in Consumer Protection Act than RERA

Q. 15         Since the pecuniary limit of National Consumer Court is Rs. one Crore, can few flats owners asking for Possession and Interest  or Principal & Interest approach National Consumer if their combined value is more than Rs. One Crore.

Ans. 15 Yes under 12(1)(C) of Consumer Protection Act, 1986.

Q. 16   Can an Association file a case on behalf of its members before the National Consumer  

Ans.16  Yes, under 12(1)(b) of Consumer Protection Act

Q.17  Can an Association file  case before the State RERA.

Ans. 17     Yes, under 12(1)(b) of Consumer Protection Act. Please refer to Amrapali Judgment CC/816/2016 upheld by SC in Civil Appeal No. 10882/2016  

Q. 18         In view of the clauses stipulating per sq.ft compensation per month by way of penalty, would it be considered as the upper limit of the compensation which can be awarded to the complainants, in the event of builder not giving the possession as per the dates mentioned in the BBA.

Ans.18      The aforesaid compensation is a unilateral and patently unfair term imposed by the builder upon the flat buyers.  Having already paid the booking amount to the builder, they become captive buyers and thus have no other option but to sign on the dotted lines, since the failure to execute the agreement unilaterally drafted by the builder and imposed upon the flat buyer is likely to result in the booking amount being forfeited by the builder.  Therefore, executing an agreement containing such a term is nothing but a consent given under coercion and cannot be said to be the result of the exercise of a free consent on the part of the flat buyer.  Moreover, a term to pay such a paltry compensation to the flat buyer in the event of default on the part of the builder, while making him pay exorbitant interest in the event of default or delay on his part is an absolutely unfair term.  In fact the incorporation of a term for payment of a paltry compensation to the buyer in the event of the failure of the builder to deliver possession within the time period committed by him had become so wide spread and rampant that the Legislature had to step in by enactment of the Real Estate (Regulation & Development) Act, 2016 to statutorily require the builder to pay compensation in the form of interest at prescribed rate in the event of the possession being delayed or the buyer deciding to quit on account of the delay on the part of the builder in delivering upon the promise made by him.  Hence irrespective of the clauses in the BBA, the buyer is entitled to a just and fair compensation for the period the possession of the flats is delayed by the opposite party.

If a paltry compensation of say Rs. 10 per s.ft per month is awarded against a builder, it may lead to dangerous consequences since the builder may be tempted not to complete the construction and divert the money collected from the flat buyers for other purposes. Paying such a meagre compensation would be a win-win situation for a builder who is likely to pay many times more if he goes to market for arranging finances which he gets by diverting the money collected from the flat buyers to other purposes.

Q.19. What is the normal compensation being awarded by the NCDRC – National Consumer Dispute Redressal Forum.

Ans. 19.    Simple interest @ 8% per annum  with effect from the committed date of possession till the date on which the possession was given or is actually offered.

Q 20.  Till what date is the interest given?

 Ans. 20.   Till the date on which the possession is actually offered and not till the date of the Occupation Certificate.

Q 21.         What is the grace period which the builder is entitled while computing the committed date of possession.

 Ans. 21.   There is no entitlement. However usually the terms of the BBA incorporate  a grace period of 3 months/6 months. It is to be noted that this grace period is a matter of agreement between the two parties i.e. builder and the buyer. Hence the builder may as well insist on no grace period.

Q. 22.        Is the compensation payable adjusted out of the additional amount, if any payable, by the complainants to the opposite party?

 Ans. 22    Yes. Usually the courts direct adjustment of the amount.

Q. 23             Is the balance amount, if any, to be paid to the builder before the flat is offered. 

Ans. 23.        The balance amount is payable while offering possession of the flat.

Q 24.         In case a possession has been taken, does the court still award the compensation and within which period is it payable to the buyer.

Ans. 24.  Yes, the buyer is entitled for compensation even if he has taken the possession and the amount is payable to him within three months of the order of the Commission. 

Q. 25         Does the Court order the cost in favour of the buyer.

Ans. 25     Yes the court has been ordering the cost of litigation to the tune of Rs. 25,000.00 in   respect of each complaint.

Q.26.         Is the existing BBA applicable in respect of projects under RERA. 

Ans. 26     No, for such projects the BBA has to be approved by the Legislature. Most of the ongoing projects have been kept out of the purview of RERA and As per section 13(2), the appropriate Government is required to specify through Rules the ‘Agreement for Sale’ to be entered into between the promoter and the allottee. This Agreement is binding on the parties, however, internal flexibility could be provided in the said Agreement for Sale, for determination / insertion of other provisions as decided between the parties for mutual benefit. Hence the existing BBA are not applicable with respect to projects under RERA.


Warm Regards 


Kuldeep Kumar Kohli 


[1] Read more at The Logical Buyer's blog: Pay delay penalty till actual possession – No more “Offer of Possession” http://www.thelogicalbuyer.com/blog/?p=1416
[2] Megh Raj vs M/S Omaxe Chandigarh Extension, SCDRC Chandigarh

No comments:

Post a Comment